Procurement route options pros and cons
This article needs more work. To help develop this article, click 'Edit this article' above.
See also: procurement route.
Contents |
[edit] Traditional contract
Good for:
- Quality – full design pre tender
- Design flexibility – variations & instructions
- Specialist subcontractors – Named specialist update to standard building contract sbc11
- Design control – through the architect / contract administrator
- Contractor's Designed Portion – such as mechanical and electrical engineering
- Cost – there may be lump sum cost benefits unless are multiple changes made
Not suited for:
- Time – require full detailed pack pre tender
- Cost – not a benefit if many changes made post tender
- Incomplete drawings – lead to delay, costs and claims of negligence
Contracts: JCT Standard Building Contract 2016, JCT Intermediate Building Contract 2016, JCT Minor Works Building Contract 2016, NEC3 ECC Option A
JCT Standard Building Contract 2016:
- Lump sum payment
- CDM
- Contractor's Designed Portion
- Named subcontractors
- Variations / instructions
- Retention
- Collateral warranties
- Termination provisions
- Pre-agreed alternative dispute resolution procedures.
[edit] Design and build
Good for:
- Time – Fast track, overlap of design and construction
- Cost – lump sum / Guaranteed maximum price
- Single point of responsibility – Contractor design and build responsibility
- Has good price certainty
- Novation – can benefit quality.
- Low risk for the client
- Variations can be accurately valued
Not suited for:
- Quality – cheapest route to meet contract specification can lead to low quality products/ build quality.
- Design flexibility – request for changes will have cost/time implications
- Contractor carries risk for construction
- Client exposed to claims for buildability
- Design could affect the buildability of the project
Contract: JCT Design and Build 2016, JCT Major Project Construction Contract 2016, NEC ECC Options A-E
JCT Design and Build 2016:
- Contractor to complete design and carry out the works.
- Lump sum / Guaranteed maximum price
- CDM
- Collateral warranties
- Termination provisions
- Retention
- Pre-agreed dispute resolution procedures
[edit] Management contracting
Good for:
- Complex / specialist projects – individually appointed packages to best suited sub-contractor
- Potential cost saving – competitive tender
- Time - it is possible to overlap design and construction
- Quality – each package subcontracted to specialist
- Design flexibility – changes can be made throughout construction, although there are potential cost implications.
Not suited for:
- Inexperienced clients – risk high
- Fixed cost - Prime cost basis per package.
- Lack of available specialists – would leave gaps in work to be undertaken.
Contract: JCT Management Building Contract 2016
- Prime cost contract
- Collateral warranties
- Sustainability
- Collaborative working
- Third party rights – such as the funder / contractor
[edit] Construction management
Good for:
- Complex / specialist projects – individually appointed packages to best suited sub-contractor
- Time - It is possible to overlap design and construction
- Design flexibility – changes can be made throughout construction, although there are potential cost implications.
- Potential cost saving – competitive tender
- Quality – each package subcontracted to specialist
- All building types
- Efficiency – Early appointment of the construction manager to aid programme
- Inexperienced client – risk high as appointing trade contractors
- Fixed cost - Prime cost basis per package.
- Lack of available specialists
Contracts:
JCT Construction Management Appointment 2016, NEC ECC Option F, Construction Management Trade Contract 1999
JCT Construction Management Appointment 2016:
CM/A
Featured articles and news
Shortage of high-quality data threatening the AI boom
And other fundamental issues highlighted by the Open Data Institute.
Data centres top the list of growth opportunities
In robust, yet heterogenous world BACS market.
Increased funding for BSR announced
Within plans for next generation of new towns.
New Towns Taskforce interim policy statement
With initial reactions to the 6 month policy update.
Heritage, industry and slavery
Interpretation must tell the story accurately.
PM announces Building safety and fire move to MHCLG
Following recommendations of the Grenfell Inquiry report.
Conserving the ruins of a great Elizabethan country house.
BSRIA European air conditioning market update 2024
Highs, lows and discrepancy rates in the annual demand.
50 years celebrating the ECA Apprenticeship Awards
As SMEs say the 10 years of the Apprenticeship Levy has failed them.
Nominations sought for CIOB awards
Celebrating construction excellence in Ireland and Northern Ireland.
EPC consultation in context: NCM, SAP, SBEM and HEM
One week to respond to the consultation on reforms to the Energy Performance of Buildings framework.
CIAT Celebrates 60 years of Architectural Technology
Find out more #CIAT60 social media takeover.
The BPF urges Chancellor for additional BSR resources
To remove barriers and bottlenecks which delay projects.
Flexibility over requirements to boost apprentice numbers
English, maths and minimumun duration requirements reduced for a 10,000 gain.
A long term view on European heating markets
BSRIA HVAC 2032 Study.
Humidity resilience strategies for home design
Frequency of extreme humidity events is increasing.
National Apprenticeship Week 2025
Skills for life : 10-16 February
Comments
This article seems to need some revision: The Management Contracting and Construction Management procurement methods appear to be the wrong way round.
Construction Management is far higher risk than Management Contracting for the client.